P3 TO P6 Units issue

Member for

22 years 9 months

Hello Minhas,

in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project

a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6

if so, you should divide the duration by 8 in P6 by using Global Change

Alexandre