Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2010-12-04 09:53 Permalink Hello Minhas,in P3 you can Hello Minhas, in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6 if so, you should divide the duration by 8 in P6 by using Global Change Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sat, 2010-12-04 09:53 Permalink Hello Minhas,in P3 you can Hello Minhas, in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6 if so, you should divide the duration by 8 in P6 by using Global Change Alexandre
Member for
22 years 9 monthsHello Minhas,in P3 you can
Hello Minhas,
in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project
a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6
if so, you should divide the duration by 8 in P6 by using Global Change
Alexandre