About Baseline and additional task

Member for

15 years 6 months

Baseline is a formal document and can’t be changed without going through the change management process. Changes should be incorporated in the ‘current schedule’ and if it is delaying the critical path then the delay has to be evaluated for an extension of time or acceleration. Once approved the current version will be converted to a baseline say BL-0002.



Let me know if you have any questions. thanks.



R

Member for

16 years 11 months

Hi Zakir



Remember that any baseline is not 100% concrete,depending on the project team and field condition the baseline tends to change and hence becomes dynamic nature.



The new task which you have come across can be incorporated in the baseline and keep updating and check the status of the project finish date.



Every time you update the schedule based on the nature of input the critical path tends to change ,keep an eye in it always

Member for

19 years 10 months

Hi Zakir



In P3 I beleive they are called "target" programmes.



How many Targets can P3 display?



Perhaps you can "Target" only the new tasks and display both on the chart.



In modern software such as PowerProject you can "merge" new tasks into the existing Baseline.



Best regards



Mike Testro