UPDATE PROGRESS MANUALLY

Member for

19 years

Vex,

Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.

Member for

15 years 3 months

hye anoon



thanks for the suggestion..

how to update the progress each activity if not based on duration and just based on pysical percentage

Member for

19 years 1 month

Vex,



That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?