Primavera Project Planner - P3 Member for 15 years 3 months Member for 15 years 4 months Submitted by vex zex on Thu, 2010-07-22 22:46 Permalink RE: UPDATE PROGRESS MANUALLY thanx fren Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-07-22 21:42 Permalink RE: UPDATE PROGRESS MANUALLY Vex, Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple. Member for 15 years 3 months Member for 15 years 4 months Submitted by vex zex on Thu, 2010-07-22 21:29 Permalink RE: UPDATE PROGRESS MANUALLY hye anoon thanks for the suggestion.. how to update the progress each activity if not based on duration and just based on pysical percentage Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Thu, 2010-07-22 08:12 Permalink RE: UPDATE PROGRESS MANUALLY Vex, That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)? Log in or register to post comments
Member for 15 years 3 months Member for 15 years 4 months Submitted by vex zex on Thu, 2010-07-22 22:46 Permalink RE: UPDATE PROGRESS MANUALLY thanx fren
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-07-22 21:42 Permalink RE: UPDATE PROGRESS MANUALLY Vex, Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.
Member for 15 years 3 months Member for 15 years 4 months Submitted by vex zex on Thu, 2010-07-22 21:29 Permalink RE: UPDATE PROGRESS MANUALLY hye anoon thanks for the suggestion.. how to update the progress each activity if not based on duration and just based on pysical percentage
Member for 19 years 1 month Member for 19 years 1 month Submitted by Anoon Iimos on Thu, 2010-07-22 08:12 Permalink RE: UPDATE PROGRESS MANUALLY Vex, That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?
Member for
15 years 3 monthsRE: UPDATE PROGRESS MANUALLY
thanx fren
Member for
19 yearsRE: UPDATE PROGRESS MANUALLY
Vex,
Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.
Member for
15 years 3 monthsRE: UPDATE PROGRESS MANUALLY
hye anoon
thanks for the suggestion..
how to update the progress each activity if not based on duration and just based on pysical percentage
Member for
19 years 1 monthRE: UPDATE PROGRESS MANUALLY
Vex,
That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?