How to Set up cut-off date in P3

Member for

22 years 9 months

Anbin,

you are right, I was confusing with the "New project" window; your solution is the best one, of course

Alexandre

Member for

16 years 4 months

Dear Angel Cruz,

I find another Option also which is very easy

Data->Calender->Click Global Calender->Standard->Week start on -> Change to Saturday

I tried it Just Now it Work

Regards

Anbin

Member for

16 years 4 months

Dear Alexandre,



I tried your solution but could not find any option to change the 1st day of the week to Saturday..



Could you please expain me in detail.





With Thanks & Regards,



Anbin Ponnith

Member for

22 years 9 months

Hi Angel and Anbin,

I guess it would be easier to use Tools, Project Utilities, Copy, and copy the current project to a new one in which the 1st day of week is Saturday

You would not have to copy the data dictionary, as P3 would do it automatically

Alexandre

Member for

16 years 4 months

Hai Angel Cruz

U try the Following Option

1.First Create a new Project(ABC)in that give Week start on Saturday

2.Open your Current Project Select all Activities

3.Click Tools->Fragnet->Store Fragnet->Type Id->Type Title

4.Open the New Project (ABC)Transfer all the Dictonary Like

a.Activity code

b.Resource

c.WBS

5.Tools ->Fragnet->Restore Fragnet->Select Correct ID u Typed Before

6.Select Rename Duplicate Only -> OK

7.Now u Can see the New Project Similar to the Current Project

8.Now U can Try Tabular Report

I Hope it works

Regards

Anbin