Because the metrics is meaningless it does not matter how you update, anyway it will still be nonsense. You can use a single resource a single activity that span the whole job duration, assign a predefined curve and you will get equally invalid measure with less effort, if this is the idea. With P3 you will get a meaningless S-Curve with early and late dates at the click of the mouse, at this P3 is so good that even meaningless is easy.
If you stick to PP in a few months you will be throwing dirty water at me, and both will laugh, believe me here you will get good at planning, keep asking here.
Best Regards,
Rafael
Member for
15 years 5 months
Member for15 years6 months
Submitted by Yaser A. Al-Bustanji on Thu, 2010-05-20 17:50
Member for
16 years 11 monthsRE: how can i obtain s curve
Hi to all
In the tools ,option , graphical reports there will be choices early & late, select which ever you need
Member for
18 years 3 monthsRE: how can i obtain s curve
use tabular report tabular
or use graphic report with labels
Member for
15 years 5 monthsRE: how can i obtain s curve
how to set up S-curve in P3 obtaining Late Dates using tabular reports resouce loading?
Member for
21 years 8 monthsRE: how can i obtain s curve
Yaser,
Because the metrics is meaningless it does not matter how you update, anyway it will still be nonsense. You can use a single resource a single activity that span the whole job duration, assign a predefined curve and you will get equally invalid measure with less effort, if this is the idea. With P3 you will get a meaningless S-Curve with early and late dates at the click of the mouse, at this P3 is so good that even meaningless is easy.
If you stick to PP in a few months you will be throwing dirty water at me, and both will laugh, believe me here you will get good at planning, keep asking here.
Best Regards,
Rafael
Member for
15 years 5 monthsRE: how can i obtain s curve
thank you for answer but during updating what i do
Member for
18 years 3 monthsRE: how can i obtain s curve
you want scurve without resource or cost?
if you are in a hurry atleast add one resource for all activities and make BQ EQ OD