how can i obtain s curve

Member for

16 years 11 months

Hi to all



In the tools ,option , graphical reports there will be choices early & late, select which ever you need

Member for

18 years 3 months

use tabular report tabular





or use graphic report with labels

Member for

15 years 5 months

how to set up S-curve in P3 obtaining Late Dates using tabular reports resouce loading?

Member for

21 years 8 months

Yaser,



Because the metrics is meaningless it does not matter how you update, anyway it will still be nonsense. You can use a single resource a single activity that span the whole job duration, assign a predefined curve and you will get equally invalid measure with less effort, if this is the idea. With P3 you will get a meaningless S-Curve with early and late dates at the click of the mouse, at this P3 is so good that even meaningless is easy.



If you stick to PP in a few months you will be throwing dirty water at me, and both will laugh, believe me here you will get good at planning, keep asking here.



Best Regards,

Rafael

Member for

15 years 5 months

thank you for answer but during updating what i do

Member for

18 years 3 months

you want scurve without resource or cost?



if you are in a hurry atleast add one resource for all activities and make BQ EQ OD