what i dont understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !
best regards
Mimoune
Member for
23 years
Member for23 years
Submitted by Craig Brough on Tue, 2010-05-11 18:01
Member for
19 yearsRE: how P3 summarize resource percent complete
thanks every body for your reply
best regards
Member for
17 yearsRE: how P3 summarize resource percent complete
Hi mimoune
in fact P3 calculate the average of ressources (la moyenne des ressources).
A+
Member for
19 yearsRE: how P3 summarize resource percent complete
Mimoune,
P3 calculate resource percent complete by resource proportion or weightings.
ex:Act1 have 2 resource with diff resource % complete
R1 = 40 units * 20% = 8 unit
R2 = 80 units * 25% = 20 unit
R/C % complete = (8+20)/(40+80) = 23.33% or 23%
Member for
19 yearsRE: how P3 summarize resource percent complete
thanks craig
what i dont understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !
best regards
Mimoune
Member for
23 yearsRE: how P3 summarize resource percent complete
Hi
I have not P3 open right now but here is a starter for 10 (or 2):
Group & Sort by resource and set the columns to display % complete.
Or, Export activity data grouped by resource. Export Total budget Quantity, Actual, and remaining and you can derive % Complete from this
Hope this helps.
Craig