how P3 summarize resource percent complete

Member for

19 years

Mimoune,

P3 calculate resource percent complete by resource proportion or weightings.

ex:Act1 have 2 resource with diff resource % complete

R1 = 40 units * 20% = 8 unit

R2 = 80 units * 25% = 20 unit

R/C % complete = (8+20)/(40+80) = 23.33% or 23%

Member for

19 years

thanks craig



what i don’t understand is when you show resource percent complete on a column, and you have two resources assigned to one activity, how P3 calculate the percent complete for the two resource together !



best regards

Mimoune

Member for

23 years

Hi



I have not P3 open right now but here is a starter for 10 (or 2):



Group & Sort by resource and set the columns to display % complete.



Or, Export activity data grouped by resource. Export Total budget Quantity, Actual, and remaining and you can derive % Complete from this



Hope this helps.



Craig