SS FF relationships...& progress updation

Member for

21 years 8 months

Split updating r1



Under discontinuous updating you should get the above, the software should respect driving logic relationships as well as resource dependancies, should respect multiple splits each with different start and finish dates, different costs, quantities, volume of work …etc, and it should display true remaining duration where it belongs as per CPM computations.



The following is a sample of an even more discountinuous update, if this is how it happened this is what you should report.



UCE



I believed only SureTrak would allow for a single split while P3 would allow for multiple splits.



P3 have an option to automate activity splitting but is kind of rudimentary, details are lost, and must be applied to all or none. The correct way is for you to decide when and how to split. Whenever you have a FF relationship you should investigate the possibility of the need for splitting, then you decide on a per activity basis if splitting or not, in how many segments and how long each segment.



In the event you decide to split the activity, the updating of your activities should allow you to display discontinuous actuals on each segment.