I have a recovery program and the activities have some actual start dates. The activity duration type assigned is fixed duration and units.
Resources assignments have - Preserve units, duration and units/times assigned.
but when i check the resource usage spread sheet, in updated activities, the Actual units + remaining units doesnt match to budgeted units. i have assigned resources as budgeted units.
Can anybody help me out
regards
ajeej
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Wed, 2010-05-26 03:53
In continiuation to my problem, can you give me step by step method to produce the resourse loading report and cash flow report per month wise in P6(as in P3) exported to excel file using report wizard. I have been trying too much but not sucessful
To use resource usage spreadsheet click resource usage spreadsheet icon or select View-> Show on Bottom-> Resource Usage Spreadsheet then click the resource on the bottom left and it will display resource spread per timescale. To see all resource, highlight all resource. (see sample below)
In P3 you cannot define labor, non-labor or equipment and materials but you can name it as define labor, non-labor or equipment and materials and define a cost type. Meaning all of them are just labor therefore when imported to P6 all are recognize as labor.
You can produce earned value report using activity window (activity module) or tracking window (tracking module)
To use activity window click activity usage profile icon or select View-> Show on Bottom-> Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options and tick Earn Value, Plan Value, At Completion or anything that you wanted to show on the profile. (see sample below)
Also I have loaded equipment, Cash(BOQ amount) also as resourse. But when i export the P3 file to P6, the equipment resourse is also taken as labour. can u help me in earned value report(% value of work done) generate in P6 reports
Thanks for your reply
With warm regards
ajeej
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Mon, 2010-05-03 23:00
Member for
15 years 6 monthshai, I have a recovery
hai,
I have a recovery program and the activities have some actual start dates. The activity duration type assigned is fixed duration and units.
Resources assignments have - Preserve units, duration and units/times assigned.
but when i check the resource usage spread sheet, in updated activities, the Actual units + remaining units doesnt match to budgeted units. i have assigned resources as budgeted units.
Can anybody help me out
regards
ajeej
Member for
19 yearsRE: Migration from P3 to P6
Ajeej,
In P6, highlight all then copy (ctrl+c) and paste (ctrl+v) to excel.
Member for
15 years 6 monthsRE: Migration from P3 to P6
Dear sir,
In continiuation to my problem, can you give me step by step method to produce the resourse loading report and cash flow report per month wise in P6(as in P3) exported to excel file using report wizard. I have been trying too much but not sucessful
with regards
Ajeej
Member for
15 years 6 monthsRE: Migration from P3 to P6
Dear sir,
Thanks a lot for the information
with best regards
Ajeej
Member for
19 yearsRE: Migration from P3 to P6
Ajeej,


To use resource usage spreadsheet click resource usage spreadsheet icon or select View-> Show on Bottom-> Resource Usage Spreadsheet then click the resource on the bottom left and it will display resource spread per timescale. To see all resource, highlight all resource. (see sample below)
In P3 you cannot define labor, non-labor or equipment and materials but you can name it as define labor, non-labor or equipment and materials and define a cost type. Meaning all of them are just labor therefore when imported to P6 all are recognize as labor.
You can produce earned value report using activity window (activity module) or tracking window (tracking module)
To use activity window click activity usage profile icon or select View-> Show on Bottom-> Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options and tick Earn Value, Plan Value, At Completion or anything that you wanted to show on the profile. (see sample below)
Member for
15 years 6 monthsRE: Migration from P3 to P6
Sir,
I didnt get you. can you brief me once again.
Also I have loaded equipment, Cash(BOQ amount) also as resourse. But when i export the P3 file to P6, the equipment resourse is also taken as labour. can u help me in earned value report(% value of work done) generate in P6 reports
Thanks for your reply
With warm regards
ajeej
Member for
19 yearsRE: Migration from P3 to P6
Ajeej.
You can use the resource usage spreadsheet to see required resources per timescale.