resource loading for late S curve

Member for

16 years 11 months

Hi caner



In tabular reports select resource option in that choose tabular,select the resource you want to generate s curve early or late,In the time scale tab select late and provide none for early and target options.save it as you wish then run it. It will create a dbf file use the data generated to produce scurve