Revised Baseline

Member for

16 years 11 months

You can do impact analysis in the revised one .Make sure your delay event is after the date date of respective programme

Member for

20 years 1 month

Thanx all for your response.



It means I have to use the latest updated programme and do revision on this to make my revised programme.



And I cannot do As-planned Impact analysis. So what kind of Impact analysis should I do and how?



It looks like I still can do an impact analysis on delays which are after the data date in case of activities which have not started but for those whcih have started or completed I will have to use the baseline programme not the revised one. But sometimes the consultants donot agree to look at the baseline programme after they have approved the revised one. They prefer to do analyis on the revised one....



Whats your opinion???


Member for

16 years 11 months

Hi Azeez



when you do revised programme with actual dates i trust you would have mentioned actual dates taking in to the account of delay event which has impacted the completion date



Hence you cannot do impacted as planned method since there is no effect on the programme due to actual dates

Member for

15 years 11 months

Hi,

If you want to make a new baseline u have to take the latest updated program with actual dates and then u may revised the sequence of work or add new activites or revise the links etc.Then u make this program as new baseline 2 keeping ur original baseline same as it is.