Iam interesting in the construction of Curve S and the QURR (Quantity Unit Rate Report) for the construction of Curve S.
I am only have the next web site:www.epenaherrera.com, you neet to have the password for download the next files: controls project & controls parts, in the files teach: NOW HOW the Curse S, Ok
I know that, with Ctrl F7, but me i would like to assign a percentage of progress to be reached and not a curve from the resources, for example for a project of 3 months I forcast to achieve 21 % the first month then 43 % the second month and 36 % the third month, what gives me a S curve, and when the realization begins, i compare the % of realization of the first month with the objective to assign (21 %). Thank you
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Sun, 2010-01-03 07:28
the easiest way is to display Resource Profile at the bottom of the screen (View, Resource Profile, or Ctrl + F7); then click Display in the tiny dialog box and select Cost or Units, Early or Late Dates, Cumulative, ...; then click Select and select the resources you want
you definitely should purchase a training book on P3 and enroll for a training session
when reading your posts on PlanningPlanet, one can understand that your comprehension of the software is good, but you are still lacking some fundamentals and for sure losing a good amount of time
Member for
15 years 7 monthsRE: S curve
Iam interesting in the construction of Curve S and the QURR (Quantity Unit Rate Report) for the construction of Curve S.
I am only have the next web site:www.epenaherrera.com, you neet to have the password for download the next files: controls project & controls parts, in the files teach: NOW HOW the Curse S, Ok
Sincely Reggards
from Mexico.
Mu E-mail ID: ccarrillohdz@hotmail.com or carloschdz@live.com.mx
Member for
16 yearsRE: S curve
I know that, with Ctrl F7, but me i would like to assign a percentage of progress to be reached and not a curve from the resources, for example for a project of 3 months I forcast to achieve 21 % the first month then 43 % the second month and 36 % the third month, what gives me a S curve, and when the realization begins, i compare the % of realization of the first month with the objective to assign (21 %). Thank you
Member for
22 years 9 monthsRE: S curve
Hello Ibrahim,
the easiest way is to display Resource Profile at the bottom of the screen (View, Resource Profile, or Ctrl + F7); then click Display in the tiny dialog box and select Cost or Units, Early or Late Dates, Cumulative, ...; then click Select and select the resources you want
you definitely should purchase a training book on P3 and enroll for a training session
when reading your posts on PlanningPlanet, one can understand that your comprehension of the software is good, but you are still lacking some fundamentals and for sure losing a good amount of time
I will send you a direct mail to explain.
Happy new year,
Alexandre