Primavera Project Planner - P3 Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-12-30 00:13 Permalink RE: Combine 2 Revision is it possible? Go to gantt chart area, right click -> select Bars (OR use Ctrl F11) and then under defined bars section, u can define current and target bars. Select the position 1/2 :-) Member for 21 years 9 months Member for 21 years 9 months Submitted by Pacifico Pallasigui on Sun, 2009-12-27 14:00 Permalink RE: Combine 2 Revision is it possible? Kumar I have thought about that i think this is the only way but is is possible to have two summary bars reflecting the current and target? thanks Member for 17 years 1 month Member for 17 years 1 month Submitted by Santhosh kumar on Sun, 2009-12-27 11:12 Permalink RE: Combine 2 Revision is it possible? Hi Pacifico, Make Target2 of revision 2 as the 2nd target file of Revision 1.The current file should be the same for both revisions. Now you have one file with target 1 & 2 and the current file. Does this solve your problem? Regards, Santhosh Log in or register to post comments
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-12-30 00:13 Permalink RE: Combine 2 Revision is it possible? Go to gantt chart area, right click -> select Bars (OR use Ctrl F11) and then under defined bars section, u can define current and target bars. Select the position 1/2 :-)
Member for 21 years 9 months Member for 21 years 9 months Submitted by Pacifico Pallasigui on Sun, 2009-12-27 14:00 Permalink RE: Combine 2 Revision is it possible? Kumar I have thought about that i think this is the only way but is is possible to have two summary bars reflecting the current and target? thanks
Member for 17 years 1 month Member for 17 years 1 month Submitted by Santhosh kumar on Sun, 2009-12-27 11:12 Permalink RE: Combine 2 Revision is it possible? Hi Pacifico, Make Target2 of revision 2 as the 2nd target file of Revision 1.The current file should be the same for both revisions. Now you have one file with target 1 & 2 and the current file. Does this solve your problem? Regards, Santhosh
Member for
18 years 5 monthsRE: Combine 2 Revision is it possible?
Go to gantt chart area, right click -> select Bars (OR use Ctrl F11) and then under defined bars section, u can define current and target bars.
Select the position 1/2
:-)
Member for
21 years 9 monthsRE: Combine 2 Revision is it possible?
Kumar
I have thought about that i think this is the only way but is is possible to have two summary bars reflecting the current and target?
thanks
Member for
17 years 1 monthRE: Combine 2 Revision is it possible?
Hi Pacifico,
Make Target2 of revision 2 as the 2nd target file of Revision 1.The current file should be the same for both revisions.
Now you have one file with target 1 & 2 and the current file.
Does this solve your problem?
Regards,
Santhosh