Links in P3.1

Member for

17 years 1 month

Dear Safak,



Thanks.That seems to be the only feasible solution.


Member for

17 years 5 months

Dear Santhosh,



"Store Fragnet" for the activities you want to keep internal relations, then delete the activities from the schedule and use "Retrieve Fragnet" to implant the activity group to the schedule again. You will get rid of the relations from out of the selected group.



Reagards,



Safak