Primavera Project Planner - P3 Member for 16 years 4 months Member for 16 years 5 months Submitted by Anbin Ponnith on Wed, 2009-12-16 04:22 Permalink RE: Schedule Percentage complete. Dear Osama, Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports. Is there any solution. With Thanks & Regards, Anbin Ponnith Member for 18 years 8 months Member for 18 years 8 months Submitted by Osama Warid on Tue, 2009-12-15 14:39 Permalink RE: Schedule Percentage complete. I think you do it by using global change Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-12-09 01:02 Permalink RE: Schedule Percentage complete. Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need Performance completion = actual percentage you plug in activity form and press F9 you could show both in activity column based on that you could do it in excel Log in or register to post comments
Member for 16 years 4 months Member for 16 years 5 months Submitted by Anbin Ponnith on Wed, 2009-12-16 04:22 Permalink RE: Schedule Percentage complete. Dear Osama, Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports. Is there any solution. With Thanks & Regards, Anbin Ponnith
Member for 18 years 8 months Member for 18 years 8 months Submitted by Osama Warid on Tue, 2009-12-15 14:39 Permalink RE: Schedule Percentage complete. I think you do it by using global change
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-12-09 01:02 Permalink RE: Schedule Percentage complete. Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need Performance completion = actual percentage you plug in activity form and press F9 you could show both in activity column based on that you could do it in excel
Member for
16 years 4 monthsRE: Schedule Percentage complete.
Dear Osama,
Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports.
Is there any solution.
With Thanks & Regards,
Anbin Ponnith
Member for
18 years 8 monthsRE: Schedule Percentage complete.
I think you do it by using global change
Member for
16 years 11 monthsRE: Schedule Percentage complete.
Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need
Performance completion = actual percentage you plug in activity form and press F9
you could show both in activity column based on that you could do it in excel