Schedule Percentage complete.

Member for

16 years 4 months

Dear Osama,



Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports.







Is there any solution.



With Thanks & Regards,



Anbin Ponnith

Member for

16 years 11 months

Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need



Performance completion = actual percentage you plug in activity form and press F9



you could show both in activity column based on that you could do it in excel