Primavera Project Planner - P3 Member for 16 years Member for 16 years Submitted by bryc ali on Wed, 2009-11-04 13:45 Permalink RE: Converting WBS to Activity Codes Its very simple, you can use menu, tools; global change, after that you add a new global change (GL-09), after i suppose that Iam create an activity code (CWBS) copy of WBS,i put, if CWBS EQ "" then CWBS EQ WBS after that you make a RUN Log in or register to post comments
Member for 16 years Member for 16 years Submitted by bryc ali on Wed, 2009-11-04 13:45 Permalink RE: Converting WBS to Activity Codes Its very simple, you can use menu, tools; global change, after that you add a new global change (GL-09), after i suppose that Iam create an activity code (CWBS) copy of WBS,i put, if CWBS EQ "" then CWBS EQ WBS after that you make a RUN
Member for
16 yearsRE: Converting WBS to Activity Codes
Its very simple, you can use menu, tools; global change, after that you add a new global change (GL-09), after i suppose that Iam create an activity code (CWBS) copy of WBS,i put,
if CWBS EQ ""
then CWBS EQ WBS
after that you make a RUN