Planned value cost BCWS

Member for

16 years 11 months

you r most welcome



you could keep your approved baseline as target and update the baseline programme using actual dates .Then in F7 option choose budget where you could get planned value and earned value

Member for

16 years

Thanks Shahul.



So I need to schedule my programm.



To compare planned and earned value. meaning i will do two programs, the current and target program..

Please help. thanks

Member for

16 years 11 months

Hi

Once you plug in actual percentage completion you could move data date using schedule option f9 by mentioning a specific date .



To compare planned and earned value you need to set targets to you programme