Primavera Project Planner - P3 Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-10-21 08:01 Permalink RE: Planned value cost BCWS you r most welcome you could keep your approved baseline as target and update the baseline programme using actual dates .Then in F7 option choose budget where you could get planned value and earned value Member for 16 years Member for 16 years 1 month Submitted by James bid on Wed, 2009-10-21 03:53 Permalink RE: Planned value cost BCWS Thanks Shahul. So I need to schedule my programm. To compare planned and earned value. meaning i will do two programs, the current and target program.. Please help. thanks Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Tue, 2009-10-20 01:29 Permalink RE: Planned value cost BCWS Hi Once you plug in actual percentage completion you could move data date using schedule option f9 by mentioning a specific date . To compare planned and earned value you need to set targets to you programme Log in or register to post comments
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-10-21 08:01 Permalink RE: Planned value cost BCWS you r most welcome you could keep your approved baseline as target and update the baseline programme using actual dates .Then in F7 option choose budget where you could get planned value and earned value
Member for 16 years Member for 16 years 1 month Submitted by James bid on Wed, 2009-10-21 03:53 Permalink RE: Planned value cost BCWS Thanks Shahul. So I need to schedule my programm. To compare planned and earned value. meaning i will do two programs, the current and target program.. Please help. thanks
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Tue, 2009-10-20 01:29 Permalink RE: Planned value cost BCWS Hi Once you plug in actual percentage completion you could move data date using schedule option f9 by mentioning a specific date . To compare planned and earned value you need to set targets to you programme
Member for
16 years 11 monthsRE: Planned value cost BCWS
you r most welcome
you could keep your approved baseline as target and update the baseline programme using actual dates .Then in F7 option choose budget where you could get planned value and earned value
Member for
16 yearsRE: Planned value cost BCWS
Thanks Shahul.
So I need to schedule my programm.
To compare planned and earned value. meaning i will do two programs, the current and target program..
Please help. thanks
Member for
16 years 11 monthsRE: Planned value cost BCWS
Hi
Once you plug in actual percentage completion you could move data date using schedule option f9 by mentioning a specific date .
To compare planned and earned value you need to set targets to you programme