Primavera Project Planner - P3 Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-09-09 06:48 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Many thanks Mr.Raviraj Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:43 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 http://www.ronwinterconsulting.com/Longest_Path_Value.pdf Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:39 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Or at best, u can drop a mail / PP to Ron Winter. He has submitted one very good paper on "Longest Path V/s Critical Path" few years before. I dont have it now, but thats the best stuff, i got till date on this issue. Cheers, Rav Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:37 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Yes, there is a difference Check the link below http://scheduleanalyzer.com/sa_long_theory.htm Log in or register to post comments
Member for 16 years 11 months Member for 16 years 11 months Submitted by Shah. HB on Wed, 2009-09-09 06:48 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Many thanks Mr.Raviraj
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:43 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 http://www.ronwinterconsulting.com/Longest_Path_Value.pdf
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:39 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Or at best, u can drop a mail / PP to Ron Winter. He has submitted one very good paper on "Longest Path V/s Critical Path" few years before. I dont have it now, but thats the best stuff, i got till date on this issue. Cheers, Rav
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2009-09-09 06:37 Permalink RE: Any Diff. b/w longest pat & total float equals to 0 Yes, there is a difference Check the link below http://scheduleanalyzer.com/sa_long_theory.htm
Member for
16 years 11 monthsRE: Any Diff. b/w longest pat & total float equals to 0
Many thanks Mr.Raviraj
Member for
18 years 5 monthsRE: Any Diff. b/w longest pat & total float equals to 0
http://www.ronwinterconsulting.com/Longest_Path_Value.pdf
Member for
18 years 5 monthsRE: Any Diff. b/w longest pat & total float equals to 0
Or at best, u can drop a mail / PP to Ron Winter. He has submitted one very good paper on "Longest Path V/s Critical Path" few years before.
I dont have it now, but thats the best stuff, i got till date on this issue.
Cheers,
Rav
Member for
18 years 5 monthsRE: Any Diff. b/w longest pat & total float equals to 0
Yes, there is a difference
Check the link below
http://scheduleanalyzer.com/sa_long_theory.htm