Primavera Project Planner - P3 Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Mon, 2009-08-24 05:17 Permalink RE: Calendar problem message Stephen Check the Clendar start dat under Data --> select "Global" --> Standard --> Calendar Start Regards Dieter Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2009-08-24 03:21 Permalink RE: Calendar problem message Hi Is this a P3 or P6 problem?? I suggest you check with any activities have any "Must finish Contraint HTH Regards Alex Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Mon, 2009-08-24 05:17 Permalink RE: Calendar problem message Stephen Check the Clendar start dat under Data --> select "Global" --> Standard --> Calendar Start Regards Dieter
Member for 22 years 8 months Member for 22 years 9 months Submitted by Alex Wong on Mon, 2009-08-24 03:21 Permalink RE: Calendar problem message Hi Is this a P3 or P6 problem?? I suggest you check with any activities have any "Must finish Contraint HTH Regards Alex
Member for
18 years 9 monthsRE: Calendar problem message
Stephen
Check the Clendar start dat under
Data --> select "Global" --> Standard --> Calendar Start
Regards
Dieter
Member for
22 years 8 monthsRE: Calendar problem message
Hi
Is this a P3 or P6 problem??
I suggest you check with any activities have any "Must finish Contraint
HTH
Regards
Alex