The target or baseline has been asigned, All I need to know is the number of days elapsed between the early finish of baseline and early finish of the current program (Time Varience). Actually, it can be determined through bar chart but it is impractical to check it one by one. Is it possible in P3 to reflect it on the columns list? Any options?
Thanks,
Albert
Member for
19 years
Member for19 years
Submitted by mimoune djouallah on Mon, 2009-06-29 08:05
Member for
19 yearsRE: Number of Days Delayed
HI
i guess yes, see variance target 1, early finish
mimoune
btw, HTH: hope this help.
Member for
17 years 4 monthsRE: Number of Days Delayed
Hi HTH,
The target or baseline has been asigned, All I need to know is the number of days elapsed between the early finish of baseline and early finish of the current program (Time Varience). Actually, it can be determined through bar chart but it is impractical to check it one by one. Is it possible in P3 to reflect it on the columns list? Any options?
Thanks,
Albert
Member for
19 yearsRE: Number of Days Delayed
you need to assign a target to do that;)
HTH