Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2009-05-12 16:06 Permalink RE: Copy parts of project Hello Arjan, oh no, you wont do it this way, you will only have a picture of the select tasks in the barchart! use Fragnets instead: Select the tasks to copy go to Tools, Fragnets Store the tasks in a fragnet open the new project Retrieve the fragnet make any needed modifications Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2009-05-12 16:06 Permalink RE: Copy parts of project Hello Arjan, oh no, you wont do it this way, you will only have a picture of the select tasks in the barchart! use Fragnets instead: Select the tasks to copy go to Tools, Fragnets Store the tasks in a fragnet open the new project Retrieve the fragnet make any needed modifications Alexandre
Member for
22 years 9 monthsRE: Copy parts of project
Hello Arjan,
oh no, you wont do it this way, you will only have a picture of the select tasks in the barchart!
use Fragnets instead:
Select the tasks to copy
go to Tools, Fragnets
Store the tasks in a fragnet
open the new project
Retrieve the fragnet
make any needed modifications
Alexandre