Import/ Export data in P3

Member for

17 years 2 months

Dear Alex,



Excellent! It works. Thank you so much.


Member for

22 years 9 months

Lalith

do you have the original cd of P3?

if yes, use the ACTIVITY.XLS file found in the RA folder;

if no:

do you have a valid SN and maintainance contract for your P3 license?

if yes, dig into the Knowledbase on www.primavera.com website and download the Excel files

if no, do as follows

open a P3 project

go to Tools, Project Utilities, Export

select the Schedule Data to Lotus to build a file model that Excel will be able to use

open the WK1 file in Excel (please!!! do not use Excel 2007)

delete all the data, be careful to keep the first four rows in the Excel sheet

key in any desired data in the corresponding column

save the file as a WK1 file

close the file

import the data in P3 by Tools, Project Utilities, Import

Alexandre