Storing Period Performance

Member for

17 years 5 months

Dear Bobo,



If you did not store at every update the situation will be like this:



week 1: 20% progress

week 2: 30% progress

week 4: 40% progress



If you did not store each. When you have a Weekly histogram for resources. Then it will show you.



week 1: 30%

week 2: 30%

week 3: 30%



Regards,



Safak

Member for

22 years 9 months

Bobo,

by using "store period performance", you know how much you have worked and spent since the last update

I do not think it is usefull for the project period before the last update

let’s say you update your project every monday and today is saturday: "Actual this period" displays actual work and actual cost between the last two mondays; "Actual" displays actual work and actual cost since the project start

Hope this helps

Alexandre