Primavera Project Planner - P3 Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2009-03-12 11:44 Permalink RE: SureTrak - data date line does not fall directly below Change your Data Date and or Project Start Date to be on Sunday as ordinal dates count start on the first day of the calendars week, ie. on Sunday. Log in or register to post comments
Member for 21 years 8 months Member for 21 years 8 months Submitted by Rafael Davila on Thu, 2009-03-12 11:44 Permalink RE: SureTrak - data date line does not fall directly below Change your Data Date and or Project Start Date to be on Sunday as ordinal dates count start on the first day of the calendars week, ie. on Sunday.
Member for
21 years 8 monthsRE: SureTrak - data date line does not fall directly below
Change your Data Date and or Project Start Date to be on Sunday as ordinal dates count start on the first day of the calendars week, ie. on Sunday.