Create an S-Curve based on Sched % Comp in P3 v3.1?

Member for

17 years 3 months

Dear John,



Go to Display screen,

Select

Type = cost

Timer Interval = Months

Remove check from Histogram

Select Total from "Resource Profile/ table"



Then you can select what you want to see for each resource or for all.



Best,



Samer