Select INT4 and click OPEN when you want to open the whole group of projects
Select AR07 and click OPEN when you want to open this project only
You will have to assign the same WBS and Activity Codes to AR07 and BU09 than in the other projects if you want to display these 2 projects with the whole group.
Refer to the APEX projects group as an example.
Cheers,
Alexandre
Member for
16 years 11 months
Member for16 years11 months
Submitted by Ernani Garena on Mon, 2009-01-26 06:27
Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Mon, 2009-01-26 05:56
The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Mon, 2009-01-26 03:08
do you 2 projects already exist? then use the Copy command to copy these projects to new projects; at the bottom of the dialog box, enter the name (4 digits) of the project group you want to associate thes 2 projects to
Member for
22 years 9 monthsRE: create project into sub-project
Select INT4 and click OPEN when you want to open the whole group of projects
Select AR07 and click OPEN when you want to open this project only
You will have to assign the same WBS and Activity Codes to AR07 and BU09 than in the other projects if you want to display these 2 projects with the whole group.
Refer to the APEX projects group as an example.
Cheers,
Alexandre
Member for
16 years 11 monthsRE: create project into sub-project
Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?
Member for
22 years 9 monthsRE: create project into sub-project
Click Tools, Project Utilities, Copy
Browse to AR07
In the "Project Group" field, enter INT4
In the "project Name" field, enter AR07
In the "Project ID" field, enter a 2 digit ID (refer to HELP for more explanations)
Same procedure for BU09
You will then delete the source projects if you wish
Alexandre
Member for
16 years 11 monthsRE: create project into sub-project
Name Number/Version Title
AR07 Target R07 - Al Rigga Station
BU09 Target R09 - Burjuman Station
INT4 OG Stations Accelerated Program- Rev05
ALQU Target 17-AlQuoz
BUIS Target 16-Business Bay
DUBL Target 26-Dubal
The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!
Member for
22 years 9 monthsRE: create project into sub-project
Ernani,
do you 2 projects already exist? then use the Copy command to copy these projects to new projects; at the bottom of the dialog box, enter the name (4 digits) of the project group you want to associate thes 2 projects to
Alexandre