create project into sub-project

Member for

22 years 9 months

Select INT4 and click OPEN when you want to open the whole group of projects

Select AR07 and click OPEN when you want to open this project only

You will have to assign the same WBS and Activity Codes to AR07 and BU09 than in the other projects if you want to display these 2 projects with the whole group.

Refer to the APEX projects group as an example.

Cheers,

Alexandre

Member for

16 years 11 months

Thanks a lot, it works! But how will it appear under INT4 when under open dialog box? If however I want to open just AR07 or BU09 without opening INT4?

Member for

22 years 9 months

Click Tools, Project Utilities, Copy

Browse to AR07

In the "Project Group" field, enter INT4

In the "project Name" field, enter AR07

In the "Project ID" field, enter a 2 digit ID (refer to HELP for more explanations)

Same procedure for BU09

You will then delete the source projects if you wish

Alexandre

Member for

16 years 11 months

Name Number/Version Title

AR07 Target R07 - Al Rigga Station

BU09 Target R09 - Burjuman Station

INT4 OG Stations Accelerated Program- Rev05

ALQU Target 17-AlQuoz

BUIS Target 16-Business Bay

DUBL Target 26-Dubal



The open project dialog box looks like above. I want to put AR07 and BU09 wihin INT4 in order that AR07 and BU09 will be within INT4 Project. ALQU, BUIS and DUBL were already within INT4 Project. How can I do that? Thank you very much!

Member for

22 years 9 months

Ernani,

do you 2 projects already exist? then use the Copy command to copy these projects to new projects; at the bottom of the dialog box, enter the name (4 digits) of the project group you want to associate thes 2 projects to

Alexandre