the simplest way is to create a new group file and then insert your 3 individual projects in it
you will then have to make the 3 data dictionnaries coherent.
1. Click File, New; then fill in all the fieds just the same as to create a single project; give this new "project" a start date that is good for the 3 individual projects.
2. Then, create a copy of each individual file by clicking Tools, Project Utilities, Copy: in the Project Group, enter the name of the project you have just created in step 1 above
All the individual projects being part of a group share the same data dictionnary.
Member for
22 years 9 monthsRE: Merging 3 schedules
el Hadj,
its okay; I wish you a happy new year and a happy awal al muharam afterwards
Alexandre
Member for
18 yearsRE: Merging 3 schedules
thanks alot Alex,
i used the the procedure and it is working , still i have to arrange activities and add the corerct relations
thanks
alaa
Member for
22 years 9 monthsRE: Merging 3 schedules
el hadj,
the simplest way is to create a new group file and then insert your 3 individual projects in it
you will then have to make the 3 data dictionnaries coherent.
1. Click File, New; then fill in all the fieds just the same as to create a single project; give this new "project" a start date that is good for the 3 individual projects.
2. Then, create a copy of each individual file by clicking Tools, Project Utilities, Copy: in the Project Group, enter the name of the project you have just created in step 1 above
All the individual projects being part of a group share the same data dictionnary.
mâa salama
Alexandre