Small Building Projects

Member for

17 years 11 months

Hi Maask,



Could you provide me some overviews of the project? I shall help you to work out the schedule.



Cheer,



Tom

Member for

16 years 11 months

Thank U Mr. Anoon Iimos,



I am expected for the detailed sequence of activities..



Regards



Maask

Member for

19 years 1 month

1. Preliminaries (including mobilization)

2. Layout (Survey)

3. Earthworks

4. Concrete Works

4.1 Foundation

4.2 Columns / Beams

4.3 Slabs

5. Architectural Works

6. MEP Works

7. Fit-out

8. Close-out



for task sequencing, you can define it in your schedule