There is no such facility of filtering activities using progress spotlight in primavera. Utilizing the progress spotlight gives you an ease in updating your program and in taking a look at the current activities of your project as by default it always starts in the data date.
For information dissemination to your project superiors on the current status of your project schedule, why not use a two-week lookahead or a one-month lookahead presentation. They would appreciate it more.
Member for
16 years 11 monthsRE: Progress Highlights
Great response, ill follow your advice.
Again Thanks & Cheers!
Member for
17 years 3 monthsRE: Progress Highlights
Hi Ruel,
There is no such facility of filtering activities using progress spotlight in primavera. Utilizing the progress spotlight gives you an ease in updating your program and in taking a look at the current activities of your project as by default it always starts in the data date.
For information dissemination to your project superiors on the current status of your project schedule, why not use a two-week lookahead or a one-month lookahead presentation. They would appreciate it more.
In Service,
Ferdinand