Primavera Project Planner - P3 Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Wed, 2008-11-12 07:04 Permalink RE: Importing MSP into Primavera Dieter, Thanks for your help Bob Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Fri, 2008-11-07 08:13 Permalink RE: Importing MSP into Primavera Bob You found the area with the rules already. Your item can be done by some steps: 1. Define a user defined field, e.g. u_id 2. During the first of your imports, change the rule, that "Text1" will be moved into "u_id". You may add a new rule "MSP_Imp" 3. Global change: activity id = u_id. Pay attention, the activity id must be unique within a project. Hope that will help. Dieter Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Wed, 2008-11-12 07:04 Permalink RE: Importing MSP into Primavera Dieter, Thanks for your help Bob
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Fri, 2008-11-07 08:13 Permalink RE: Importing MSP into Primavera Bob You found the area with the rules already. Your item can be done by some steps: 1. Define a user defined field, e.g. u_id 2. During the first of your imports, change the rule, that "Text1" will be moved into "u_id". You may add a new rule "MSP_Imp" 3. Global change: activity id = u_id. Pay attention, the activity id must be unique within a project. Hope that will help. Dieter
Member for
18 years 1 monthRE: Importing MSP into Primavera
Dieter,
Thanks for your help
Bob
Member for
18 years 9 monthsRE: Importing MSP into Primavera
Bob
You found the area with the rules already.
Your item can be done by some steps:
1. Define a user defined field, e.g. u_id
2. During the first of your imports, change the rule, that "Text1" will be moved into "u_id". You may add a new rule "MSP_Imp"
3. Global change: activity id = u_id.
Pay attention, the activity id must be unique within a project.
Hope that will help.
Dieter