To behave as expected, the activity should have a Hammock Activity Type, and should be linked to one predecessor with a Start to Start relationship, and to one successor with a Finish to Finish relationship (meaning that in your case the successor should be a Finish Milestone).
Member for
18 years 9 monthsRE: Dependable task duration
Hello Dan,
What you describe looks like a Hammock activity:
To behave as expected, the activity should have a Hammock Activity Type, and should be linked to one predecessor with a Start to Start relationship, and to one successor with a Finish to Finish relationship (meaning that in your case the successor should be a Finish Milestone).
Hope this helps
Jean-Philippe