Primavera Project Planner - P3 Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Mon, 2008-09-22 12:15 Permalink RE: Forecasting % Complete Using P6 Great stuff. Thanks Member for 18 years 5 months Member for 18 years 5 months Submitted by Sajid Balma on Mon, 2008-09-22 11:57 Permalink RE: Forecasting % Complete Using P6 Tools>Update Progress; choose your date & apply In schedule % complete you will get the total % as if everything going exactly the way they were planned (forecast%) Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by Bob Foden on Mon, 2008-09-22 12:15 Permalink RE: Forecasting % Complete Using P6 Great stuff. Thanks
Member for 18 years 5 months Member for 18 years 5 months Submitted by Sajid Balma on Mon, 2008-09-22 11:57 Permalink RE: Forecasting % Complete Using P6 Tools>Update Progress; choose your date & apply In schedule % complete you will get the total % as if everything going exactly the way they were planned (forecast%)
Member for
18 years 1 monthRE: Forecasting % Complete Using P6
Great stuff. Thanks
Member for
18 years 5 monthsRE: Forecasting % Complete Using P6
Tools>Update Progress; choose your date & apply
In schedule % complete you will get the total % as if everything going exactly the way they were planned (forecast%)