P3.1 Planned Percentage

Member for

20 years 9 months

Thanks Paul, that’ll do for me. Easy when you know how ... :)


Member for

24 years 6 months

I usually autostatus using progress spotlight a copy of the baseline and set it as Target 2. The % complete of this schedule will be the planned % complete.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au