Independent activity

Member for

21 years 10 months

Thanks Paul for the explanation.



Regards,



Moutaz

Member for

24 years 6 months

By default activities are "Independent" in MSP. That is when a resource is assigned to an activity then it will acknowledge the resource calendar, unless one checks the "Do not acknowledge resource calendar box". MSP does not have a equivalent to a Meeting task so they are often correctly imported as Independent. But as there are so many ways of importing a MSP schedule into P3 I am not sure they all treat the tasks the same way.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Member for

21 years 10 months

Is there any response?



regards,



Moutaz