Reviewing a schedule

Member for

20 years 3 months

In addition to Ron Winter’s guidelines,



It is also preferable to look at the contract regarding specification for planning and scheduling.



In one of the project I was involved, there was a general specification on planning and scheduling, so in my review, i just flag what was not included as per the specification.



The review of CPM is very important to look at the lofig in arriving at the CPM, it is really reasonable, no manipulation of logic, etc., etc.



Regards,

Charlie

Member for

20 years 3 months

Ron Winter indeed it is brilliant.



Do you have anything regarding reviewing a schedule during progress update



reviewing a schedule for revise baseline.



We do need some sort of a guidance for the above.



Regards,



Charlie

Member for

18 years 4 months

Excellento............ Thanks for the link.