Primavera Project Planner - P3 Member for 20 years 1 month Member for 20 years 1 month Submitted by Prabin Kumar on Mon, 2008-08-11 07:54 Permalink RE: How best can I measure Percent Completion of Tasks Hi Joel, On level 4 /5 schedule, I used to measure on BOQ basis. But on Level 3 and below its better to measure on Weight value or Unit (based on cost or resources) Prabin Log in or register to post comments
Member for 20 years 1 month Member for 20 years 1 month Submitted by Prabin Kumar on Mon, 2008-08-11 07:54 Permalink RE: How best can I measure Percent Completion of Tasks Hi Joel, On level 4 /5 schedule, I used to measure on BOQ basis. But on Level 3 and below its better to measure on Weight value or Unit (based on cost or resources) Prabin
Member for
20 years 1 monthRE: How best can I measure Percent Completion of Tasks
Hi Joel,
On level 4 /5 schedule, I used to measure on BOQ basis.
But on Level 3 and below its better to measure on Weight value or Unit (based on cost or resources)
Prabin