There is no distinction between using either Physical % or Duration % complete in order to set Performance % complete (which is how P5 calculates Earned Value)
Duration % complete DOES roll up "properly" - but I cannot imagine what you would use that for if the client understands EVA - why not just roll up Performance % complete?