Activity ID

Member for

18 years 9 months

Jineesh

If these activities belong to a project which belongs to a project group, then the first two characters are the project-id and you can’t change them. If you are still planning, then create a new project with the id "MW" and copy your activities into this project, e.g. by "merge".

Regards

Dieter

Member for

18 years 2 months

Its for P3. . could you pls explain how it is to be done? I tried global change without success . .

Member for

18 years 9 months

Jineesh

Do you need this for P3 or p3e?

Here it’s global change as well and a good help function. You must open the project in exclusive mode.

Dieter