Primavera Project Planner - P3 Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2008-05-26 16:00 Permalink RE: How Do I Rebaseline in P3.1? Daniel, open the Targets dialog, select the offending taget file in the list, then click Update and select the correct options Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2008-05-26 16:00 Permalink RE: How Do I Rebaseline in P3.1? Daniel, open the Targets dialog, select the offending taget file in the list, then click Update and select the correct options Alexandre
Member for
22 years 9 monthsRE: How Do I Rebaseline in P3.1?
Daniel,
open the Targets dialog, select the offending taget file in the list, then click Update and select the correct options