Critical Path - setting the last activity that finishes

Member for

21 years 9 months

Mr. Naveen,

I think the bigger the schedule the more important critical becomes to control teh project. If you are using Primavera, the size of schdule is not of much importance.

Member for

20 years 10 months

Ron,



I stopped reading the paper when it said its for normal sized schedules of 500 activities & over a limited period of one month. Most of the schedules that we deal with are more than 5000 to 10,000 activities. So how practical is to deal with schedules of this size when I want to determine what was the critical path ?



Regards

Naveen

Member for

21 years 9 months

I think there is another quick fix to this probelm.

Just create a Mandatory Contraint on activity on which you want the ctirical path to stop. All activities after this activity will have a float based on thier successors.

Member for

17 years 6 months

Ronald



I can’t thank you enough.



1) The answer was spot on and simple to implement.

2) The response time was amazing. I think only an hour lapsed.

3) In addition to resolving my question your paper gave me a lot better understanding on CPM and Longest Path.



Thank you again.

Regards

J

Member for

18 years 5 months

Ronald,



That was gr8,



All printed, read and glued to.......



This is something, which u can force the contractor to do, if u r working from a client side.



But, if u r from contractor side, then client will never accept these dummy activities, as these activities to be removed later on, will act as a float and client may be object to add these activities.



neway, gr8 paper.



:-)



Rav