Primavera Project Planner - P3 Member for 17 years 7 months Member for 17 years 8 months Submitted by Gerry Ampo on Thu, 2008-04-24 06:50 Permalink RE: P3.1 RESOURCE LOADING Hello Rio, Let me guess on this one... Probably,.. you have to check the settings of your resource loading report. Highlight your particular resource loading report on the menu bar,..click MODIFY.. go to FORMAT.. and check the DIVIDE BY box below. In order to yield the same quatity with the bugdet when this is set to run, the divide box should be set to "1". Otherwise, for example,.. if that box was set to "2", then this will give you half of the BQ. Hope this helps...regards. Gerry Log in or register to post comments
Member for 17 years 7 months Member for 17 years 8 months Submitted by Gerry Ampo on Thu, 2008-04-24 06:50 Permalink RE: P3.1 RESOURCE LOADING Hello Rio, Let me guess on this one... Probably,.. you have to check the settings of your resource loading report. Highlight your particular resource loading report on the menu bar,..click MODIFY.. go to FORMAT.. and check the DIVIDE BY box below. In order to yield the same quatity with the bugdet when this is set to run, the divide box should be set to "1". Otherwise, for example,.. if that box was set to "2", then this will give you half of the BQ. Hope this helps...regards. Gerry
Member for
17 years 7 monthsRE: P3.1 RESOURCE LOADING
Hello Rio,
Let me guess on this one... Probably,.. you have to check the settings of your resource loading report.
Highlight your particular resource loading report on the menu bar,..click MODIFY.. go to FORMAT.. and check the DIVIDE BY box below.
In order to yield the same quatity with the bugdet when this is set to run, the divide box should be set to "1".
Otherwise, for example,.. if that box was set to "2", then this will give you half of the BQ.
Hope this helps...regards.