Diffrence B/N P5 and P6

Member for

17 years 8 months

Thanks sir.





could you please advise me how to maintane S- curve for Resource in P5



I want to create s-curve for Labour Machine and Mat.



it is posible in p5 to show then as a seprate one.



Again Thanks

Shazia

Member for

17 years 3 months

As previously noted, review the "new in P6" information in the Help files. From a base functionality, end-user standpoint, there are really very few differences between P5 and P6.1. A lot of the enhancements came on the back-end for the client. If you are relatively new to scheduling and just learning P6.0/P6.1, then you will find the two versions virtually identical. In fact, a lot of companies still train people on P5 using P6.0 or P6.1.



It’s really more in the advanced features and the web that P5 and P6 start to differ. P6.0/P6.1 Web Access is light years ahead of where P5’s web access (aka myPrimavera) was.

Member for

17 years 6 months

Hi..Nice Man





Thanks for your valuable advise.



I did ....wbs engineering.Procurement, Construction and com.





i got a list of activity from PM



i hope i will be perform well.



Again Advise me in deatil what is resources and how it will work in programme...and how to set up them...



Thanks in Advance...



Keep well.



Shazia

Member for

18 years 9 months

Hi Shazia

If you’ll carefully read through PP, you’ll find many hints. Most important will be, to ask your senior colleagues, because every company has its own style.

Basically an epc-schedule will contain Depending on project:

- Milestones

- Overhead activities

- Engineering

+ Basic

+ Detail

- Procurement

+ Inquiry

+ Evaluation / purchase order / admin

+ Manufacturing / Tests / Expediting

+ Shipment / Customs

- Site: Mobil. / Demobil.

- Construction

+ Civil

+ ... depending on project

- Commissioning / start-up

- Warranty

The coding will depend on needs for reporting

By:

- Phase

- Equipment

- Subcontractor

- Discipline

- Company’s standard

This was just a basic example which will vary by project



Regards

Dieter

Member for

17 years 6 months

Hey, Dueter.



Nice to see your advise.

i am fresh for planning / scheduling

Could plz advise me how to set a epc schedule in P5



what are the steps...



Have a nice day

Member for

18 years 9 months

Hi Shazia

Primavera is delivered as a set of 4 cd. The third one is the documentation cd. There you can find the refManual as a pdf. The P5 manual would work with P6 as well.

By the way: This is the category for P3, your question relates to Primavera Enterprise/P3e/P4..

Regards

Dieter

Member for

17 years 6 months

Hello Dieter



Thanks so much for your response.



could you plz send me a soft copy of manual(P6) if you do have.





I am just start to play with P5 ..i am new for p5..



anyway again thanks



Shazia

Member for

18 years 9 months

Hi Shazia

P6 is the new release of P5, so no need to join a training for P6 if you are acquainted to P5. Training in P6 only would be useful, if the P5 training was of poor quality and a good location for P6-training.

If you’ll open Help in P6, there is a chapter "what’s new in P6". For me the major improvements have been:

- Better performance of some database-related actions

- Resource allocation

- Define a limit for role allocation

- XML-format

- Curtains are related to a layout.

But there are more.

Regards

Dieter