Hello Kieran



I assumed to have unlimited resources.The only constraints i have is the issuance commencement of work and the completion of work. I used SS,FF and FS. Kindly elaborate the open ended activities? I’m really new in planning and i did not have any formal study in planning. Thank you.



Regards,

Denmark

Member for

21 years 9 months

Morning Denmark (and the rest of the world!)



Do you have any intermediate constraints in the programme ie. delivery of materials start on dates etc.

Also check any open ended activities, especialy if you are using start to start logic.



Regards



Kieran