Unable to Split activity

Member for

18 years 6 months

Hi

Dieter, thanks for ur support and reply, yeah that activity had not started, the problem is solved.

Cheers



Mangesh

Member for

18 years 9 months

Hi Mangesh

I assume this activity wasn’t started. Only activities in progress you can suspend and resume.

Was this the answer to your question?

Regards

Dieter

Member for

18 years 5 months

Mangesh FYI,



In P3, if u r splitting activity, then UPT is constant for all timeperiods.



Is ur UPT constant?



Cheers,



Rav

Member for

18 years 6 months

Hi

willem,

actually i want to do resource levelling of my project and for that i want to split some activities, but when i schedule, the p3 does not split activities.

wht may be the possible reason.



Cheers



Mangesh