Primavera Project Planner - P3 Member for 18 years 6 months Member for 18 years 7 months Submitted by Mangesh Khuspe on Mon, 2008-03-24 23:37 Permalink RE: Unable to Split activity Hi Dieter, thanks for ur support and reply, yeah that activity had not started, the problem is solved. Cheers Mangesh Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Mon, 2008-03-24 19:53 Permalink RE: Unable to Split activity Hi Mangesh I assume this activity wasnt started. Only activities in progress you can suspend and resume. Was this the answer to your question? Regards Dieter Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Sun, 2008-03-23 14:22 Permalink RE: Unable to Split activity Mangesh FYI, In P3, if u r splitting activity, then UPT is constant for all timeperiods. Is ur UPT constant? Cheers, Rav Member for 18 years 6 months Member for 18 years 7 months Submitted by Mangesh Khuspe on Sun, 2008-03-23 04:16 Permalink RE: Unable to Split activity Hi willem, actually i want to do resource levelling of my project and for that i want to split some activities, but when i schedule, the p3 does not split activities. wht may be the possible reason. Cheers Mangesh Log in or register to post comments
Member for 18 years 6 months Member for 18 years 7 months Submitted by Mangesh Khuspe on Mon, 2008-03-24 23:37 Permalink RE: Unable to Split activity Hi Dieter, thanks for ur support and reply, yeah that activity had not started, the problem is solved. Cheers Mangesh
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Mon, 2008-03-24 19:53 Permalink RE: Unable to Split activity Hi Mangesh I assume this activity wasnt started. Only activities in progress you can suspend and resume. Was this the answer to your question? Regards Dieter
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Sun, 2008-03-23 14:22 Permalink RE: Unable to Split activity Mangesh FYI, In P3, if u r splitting activity, then UPT is constant for all timeperiods. Is ur UPT constant? Cheers, Rav
Member for 18 years 6 months Member for 18 years 7 months Submitted by Mangesh Khuspe on Sun, 2008-03-23 04:16 Permalink RE: Unable to Split activity Hi willem, actually i want to do resource levelling of my project and for that i want to split some activities, but when i schedule, the p3 does not split activities. wht may be the possible reason. Cheers Mangesh
Member for
18 years 6 monthsRE: Unable to Split activity
Hi
Dieter, thanks for ur support and reply, yeah that activity had not started, the problem is solved.
Cheers
Mangesh
Member for
18 years 9 monthsRE: Unable to Split activity
Hi Mangesh
I assume this activity wasnt started. Only activities in progress you can suspend and resume.
Was this the answer to your question?
Regards
Dieter
Member for
18 years 5 monthsRE: Unable to Split activity
Mangesh FYI,
In P3, if u r splitting activity, then UPT is constant for all timeperiods.
Is ur UPT constant?
Cheers,
Rav
Member for
18 years 6 monthsRE: Unable to Split activity
Hi
willem,
actually i want to do resource levelling of my project and for that i want to split some activities, but when i schedule, the p3 does not split activities.
wht may be the possible reason.
Cheers
Mangesh