Hi Brian

TF of an activity depends on the assigned calendar.

- Your activities have a calendar with 7 working days a week

- The Milestone has a calendar with 5 working days a week + a public holiday between MS and the project’s end. E.g.:

LTC Start Sep. 12 with OD=9d--> End Sep 20

Dirt Start Sep. 21 with OD=7d--> End Sep 27

Project’s end: Nov 14 with a public holiday (Oct 3, German national day) --> TF = 48days for LTC&Dirt and 33days for the MS.

OK?

Regards

Dieter


Member for

18 years 1 month

Hi Brian,



It’s not always linear!!

Check the pred. of both activities (LTC. & Dirt Excavation) and you’ll get for sure one with 33 days of total float...



Regards

JK