Primavera Project Planner - P3 Member for 18 years 1 month Member for 18 years 1 month Submitted by Brian Chan on Tue, 2008-03-18 19:25 Permalink RE: I thought I understood Total Floats Thanks, It was the calendars. All fixed now! Cheers! Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Tue, 2008-03-18 18:01 Permalink RE: I thought I understood Total Floats Hi Brian TF of an activity depends on the assigned calendar. - Your activities have a calendar with 7 working days a week - The Milestone has a calendar with 5 working days a week + a public holiday between MS and the project’s end. E.g.: LTC Start Sep. 12 with OD=9d--> End Sep 20 Dirt Start Sep. 21 with OD=7d--> End Sep 27 Project’s end: Nov 14 with a public holiday (Oct 3, German national day) --> TF = 48days for LTC&Dirt and 33days for the MS. OK? Regards Dieter Member for 18 years 1 month Member for 18 years 1 month Submitted by Johny Kesserwany on Tue, 2008-03-18 17:47 Permalink RE: I thought I understood Total Floats Hi Brian, Its not always linear!! Check the pred. of both activities (LTC. & Dirt Excavation) and youll get for sure one with 33 days of total float... Regards JK Log in or register to post comments
Member for 18 years 1 month Member for 18 years 1 month Submitted by Brian Chan on Tue, 2008-03-18 19:25 Permalink RE: I thought I understood Total Floats Thanks, It was the calendars. All fixed now! Cheers!
Member for 18 years 9 months Member for 18 years 9 months Submitted by Dieter Wambach on Tue, 2008-03-18 18:01 Permalink RE: I thought I understood Total Floats Hi Brian TF of an activity depends on the assigned calendar. - Your activities have a calendar with 7 working days a week - The Milestone has a calendar with 5 working days a week + a public holiday between MS and the project’s end. E.g.: LTC Start Sep. 12 with OD=9d--> End Sep 20 Dirt Start Sep. 21 with OD=7d--> End Sep 27 Project’s end: Nov 14 with a public holiday (Oct 3, German national day) --> TF = 48days for LTC&Dirt and 33days for the MS. OK? Regards Dieter
Member for 18 years 1 month Member for 18 years 1 month Submitted by Johny Kesserwany on Tue, 2008-03-18 17:47 Permalink RE: I thought I understood Total Floats Hi Brian, Its not always linear!! Check the pred. of both activities (LTC. & Dirt Excavation) and youll get for sure one with 33 days of total float... Regards JK
Member for
18 years 1 monthRE: I thought I understood Total Floats
Thanks,
It was the calendars.
All fixed now!
Cheers!
Member for
18 years 9 monthsRE: I thought I understood Total Floats
Hi Brian
TF of an activity depends on the assigned calendar.
- Your activities have a calendar with 7 working days a week
- The Milestone has a calendar with 5 working days a week + a public holiday between MS and the project’s end. E.g.:
LTC Start Sep. 12 with OD=9d--> End Sep 20
Dirt Start Sep. 21 with OD=7d--> End Sep 27
Project’s end: Nov 14 with a public holiday (Oct 3, German national day) --> TF = 48days for LTC&Dirt and 33days for the MS.
OK?
Regards
Dieter
Member for
18 years 1 monthRE: I thought I understood Total Floats
Hi Brian,
Its not always linear!!
Check the pred. of both activities (LTC. & Dirt Excavation) and youll get for sure one with 33 days of total float...
Regards
JK