Can you try to check the Start Point type and Finish Point type in your Target Bar Structure? There might be a chance that instead of Putting the "Target 1 early start" and the "Target 1 early finish" respectively, the "early start" and the "early finish" type was installed.
Member for
18 years 11 months
Member for18 years11 months
Submitted by Muhammad Waseem, PMP on Fri, 2008-03-07 02:20
I think you are need to define the bars properly, there is a chance that you mihgt not have check target bar in the bars setting dialog box. Otherwise there is no other setting as will move the target bar along with actuals if u have properly asigned the target to your project in Tools>Project utilities>Target.
Member for
17 years 8 monthsRE: Current schedule V/S Target
Thanks everyone for your replies i got it fixed. the replies really helped me to fix it. Thanks everyone......
Member for
17 years 7 monthsRE: Current schedule V/S Target
Hello Aloke,
Can you try to check the Start Point type and Finish Point type in your Target Bar Structure? There might be a chance that instead of Putting the "Target 1 early start" and the "Target 1 early finish" respectively, the "early start" and the "early finish" type was installed.
Member for
18 years 11 monthsRE: Current schedule V/S Target
I think you are need to define the bars properly, there is a chance that you mihgt not have check target bar in the bars setting dialog box. Otherwise there is no other setting as will move the target bar along with actuals if u have properly asigned the target to your project in Tools>Project utilities>Target.