Getting "one activity" for the longest path is different from what you said earlier about getting “no activities.”
As the article that I referenced pointed out, longest path is susceptible to error due to constraints being used. It seems probable to me that your milestone at the end of your project is constrained to finish later than any other activity in your schedule. Remove the constraint and this should clear-up the longest path problem.
You don’t need software to solve your problems. Scheduling is a matter of understanding the underlying principles of CPM theory and mathematics and applying logic and reason. Good luck!
Thank you for the information in your lecture, I am very proud that I have met you as a professional. Yet the problem is not solved and only the finish milestone shows if I use longest path method through out the filter. I was not able to develop a software like you did and surely need a lot of experience to be able to perform such development, thus I ask you to send me the software if I may use it hopefully it will help.
1- The problem doesnt show with projects that have target baselines, could it be the reason why this particular project doesnt give the longest/critical path?
2- How is it possible for me in my situation to find the critical path and the shrinking possibilities on the baseline?
With greater respect and admiration,
Yours always,
Wael
Member for
22 years 10 months
Member for22 years10 months
Submitted by Ronald Winter on Wed, 2008-03-05 10:02
Be sure that you have first computed the critical path (F9 key), or you will not have a critical path to display.
P3s implementation of the longest path has some faults that can give you odd results. You should always return at least once activity when filtering for the longest path, but the longest path may not always run from the data date to project end. The use of constraints is a major reason for this.
You may want to look at a paper that I authored some time ago on this subject titled, "Longest Path." It is posted with other papers of mine at http://ronwinterconsulting.com/published.htm. Good luck!
i ahev a challenging task, at least for me as a beginner i assume , daye3 bishakel mish tabee3eh... it is a matter over critical path , as i filter my project using longest path eq yes i get no activities . is that normal or something wrong is happening.
could it be that a baseline schedule does not have a critical path?
and finaly how could i check the probability of shrinking the schedule after finding the critical path.?
thanks alot and 3an jad indeed
Member for
18 years 1 month
Member for18 years1 month
Submitted by Johny Kesserwany on Tue, 2008-03-04 14:26
Member for
22 years 10 monthsRE: Challenging tasks
Getting "one activity" for the longest path is different from what you said earlier about getting “no activities.”
As the article that I referenced pointed out, longest path is susceptible to error due to constraints being used. It seems probable to me that your milestone at the end of your project is constrained to finish later than any other activity in your schedule. Remove the constraint and this should clear-up the longest path problem.
You don’t need software to solve your problems. Scheduling is a matter of understanding the underlying principles of CPM theory and mathematics and applying logic and reason. Good luck!
Member for
17 years 8 monthsRE: Challenging tasks
Dear Sir,
Thank you for the information in your lecture, I am very proud that I have met you as a professional. Yet the problem is not solved and only the finish milestone shows if I use longest path method through out the filter. I was not able to develop a software like you did and surely need a lot of experience to be able to perform such development, thus I ask you to send me the software if I may use it hopefully it will help.
1- The problem doesnt show with projects that have target baselines, could it be the reason why this particular project doesnt give the longest/critical path?
2- How is it possible for me in my situation to find the critical path and the shrinking possibilities on the baseline?
With greater respect and admiration,
Yours always,
Wael
Member for
22 years 10 monthsRE: Challenging tasks
Be sure that you have first computed the critical path (F9 key), or you will not have a critical path to display.
P3s implementation of the longest path has some faults that can give you odd results. You should always return at least once activity when filtering for the longest path, but the longest path may not always run from the data date to project end. The use of constraints is a major reason for this.
You may want to look at a paper that I authored some time ago on this subject titled, "Longest Path." It is posted with other papers of mine at http://ronwinterconsulting.com/published.htm. Good luck!
Member for
17 years 8 monthsRE: Challenging tasks
hello johny keefak?
i ahev a challenging task, at least for me as a beginner i assume , daye3 bishakel mish tabee3eh... it is a matter over critical path , as i filter my project using longest path eq yes i get no activities . is that normal or something wrong is happening.
could it be that a baseline schedule does not have a critical path?
and finaly how could i check the probability of shrinking the schedule after finding the critical path.?
thanks alot and 3an jad indeed
Member for
18 years 1 monthRE: Challenging tasks
Indeed !!!!