Primavera Project Planner - P3 Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Mon, 2008-01-14 07:07 Permalink RE: Adjust Working Hours Thanks JK Member for 18 years 1 month Member for 18 years 1 month Submitted by Johny Kesserwany on Sun, 2008-01-13 17:26 Permalink RE: Adjust Working Hours Hi Karim, P3 is based on working days and not on hours. P5 & P6 are hours based and any schedule converted from P3 will have the same problem. P6 too has the same bug. Regards JK Log in or register to post comments
Member for 19 years 7 months Member for 19 years 7 months Submitted by Karim Mounir on Mon, 2008-01-14 07:07 Permalink RE: Adjust Working Hours Thanks JK
Member for 18 years 1 month Member for 18 years 1 month Submitted by Johny Kesserwany on Sun, 2008-01-13 17:26 Permalink RE: Adjust Working Hours Hi Karim, P3 is based on working days and not on hours. P5 & P6 are hours based and any schedule converted from P3 will have the same problem. P6 too has the same bug. Regards JK
Member for
19 years 7 monthsRE: Adjust Working Hours
Thanks JK
Member for
18 years 1 monthRE: Adjust Working Hours
Hi Karim,
P3 is based on working days and not on hours. P5 & P6 are hours based and any schedule converted from P3 will have the same problem. P6 too has the same bug.
Regards
JK