FIN Float

Member for

18 years 1 month

Chuck,



in P3 the total float is always numeric. This columun you look at it contains ’Custom data’ values, i.e. written by the user and NOT calculated by P3.

So ask who submitted the program to list his used custom data items with their related description.



Regards

JK

Member for

22 years 9 months

Chuck,

"Fin" means "End" in French; does it help?

Alexandre

Member for

22 years 9 months

Chuck,

"Fin" means "End" in French; does it help?

Alexandre

Member for

20 years 1 month

The bar chart view that I am looking at includes a column labeled "FLT". This FLT column contains either numeric or the letters "FIN". The occurrence of "FIN" corresponds to either a constrained ES or EF - some of which are actuals and some of which are not.



Thx - CL

Member for

18 years 1 month

Hi,



What do you mean by ’FIN’?



P3 can calculate Total float in 3 different ways:

1)Most critical

2)Start Float

3)Finish float (by default)



Tools-Schedule-options



Regards

Jk