Primavera Project Planner - P3 Member for 17 years 11 months Member for 17 years 11 months Submitted by Artur Correa on Thu, 2007-11-22 08:46 Permalink RE: problem with histogram Thank you. It is working. Member for 20 years 8 months Member for 20 years 8 months Submitted by Bijaya Bajracharya on Thu, 2007-11-22 08:34 Permalink RE: problem with histogram To start with, this posting is in wrong place. Anyway the solution to your prblem is: Right-click the histogram area. Click REsource Usage Profile Options. Go to Graph tab. Additional Display Options Tick for "Calculate Average" and under "Divide interval totals by:" tick "Base on Hours per Time Period". Your histogram should now show you the number of resources. Log in or register to post comments
Member for 17 years 11 months Member for 17 years 11 months Submitted by Artur Correa on Thu, 2007-11-22 08:46 Permalink RE: problem with histogram Thank you. It is working.
Member for 20 years 8 months Member for 20 years 8 months Submitted by Bijaya Bajracharya on Thu, 2007-11-22 08:34 Permalink RE: problem with histogram To start with, this posting is in wrong place. Anyway the solution to your prblem is: Right-click the histogram area. Click REsource Usage Profile Options. Go to Graph tab. Additional Display Options Tick for "Calculate Average" and under "Divide interval totals by:" tick "Base on Hours per Time Period". Your histogram should now show you the number of resources.
Member for
17 years 11 monthsRE: problem with histogram
Thank you. It is working.
Member for
20 years 8 monthsRE: problem with histogram
To start with, this posting is in wrong place.
Anyway the solution to your prblem is:
Right-click the histogram area.
Click REsource Usage Profile Options.
Go to Graph tab. Additional Display Options
Tick for "Calculate Average" and under "Divide interval totals by:" tick "Base on Hours per Time Period".
Your histogram should now show you the number of resources.