The quickest way to display your resource loading is to use the layout screen.
In addition, you need to know that Baseline(target project) need to loaded with the correct budget as well since the tablar report uses the target project budget as the budgeted quantity.
Good Luck
Alex
Member for
18 years 6 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Tue, 2007-10-23 03:46
As I understood from your post, you have BQ for all actvities.
Load the BQ in the P#3.
Now as the BQ is in Hours and you need the histogram in Man you need to Plot the Histogram with ordinal dates by dividing it by 10 for 10 hours working.
I just did the trial run and it worked for my project, hope it helps you also.
Regards,
Ashraf
Member for
18 years 2 months
Member for18 years3 months
Submitted by Ranganathan Ra… on Sun, 2007-10-21 10:24
FIRST OF ALL, 200/10=20 and not 10. (Check ur post)
In Tools -> Graphic Reports- Resource and Cost Graphics-Histogram with Ordinal rates, go to DATE TAB; There is option, TIMESCALE and Title each. Change it to Days and Week respectively.
You will get in histogram as no. of people required per day. (i.e. units per day)
Member for
22 years 8 monthsRE: Histogram- Resource
Ranga
The quickest way to display your resource loading is to use the layout screen.
In addition, you need to know that Baseline(target project) need to loaded with the correct budget as well since the tablar report uses the target project budget as the budgeted quantity.
Good Luck
Alex
Member for
18 years 6 monthsRE: Histogram- Resource
Hi Ranga,
As I understood from your post, you have BQ for all actvities.
Load the BQ in the P#3.
Now as the BQ is in Hours and you need the histogram in Man you need to Plot the Histogram with ordinal dates by dividing it by 10 for 10 hours working.
I just did the trial run and it worked for my project, hope it helps you also.
Regards,
Ashraf
Member for
18 years 2 monthsRE: Histogram- Resource
Hi Ravi
Yes it should be 200/10=20.
This activity start date is 11 May 2009-25 May 2009
I changed the time scale and title as days and week
it says too many interval tofit within time scale
In Tools-Graphic Reports-Resource and Cost Graphics-Histogram with Ordinal rates
Resource Selection tab
Group :#1
Profile if :EQ
Low value resource :(name of the resource)
Content tab
Schedule : current
Show data: Resource
Dates: Early
divide by: 10
Curve: Histogram
Histogram format:Bar
Display data values : checked
Date tab:
Display date: Calender
Time period: (Project) Start date- 1 jan 07
(Project) End date-19 June 09
Title each: Month
Timescale: week
Where i am doing wrong?
I have to select units per day and divide by 10 in y axis and in X axis i months like jan,feb,march for the histogram
Can u please guide me
Member for
18 years 5 monthsRE: Histogram- Resource
Ranga,
FIRST OF ALL, 200/10=20 and not 10. (Check ur post)
In Tools -> Graphic Reports- Resource and Cost Graphics-Histogram with Ordinal rates, go to DATE TAB; There is option, TIMESCALE and Title each. Change it to Days and Week respectively.
You will get in histogram as no. of people required per day. (i.e. units per day)
Hope it is clear.
Cheers,
Rav